Tuesday, November 30, 2010

Work is substantially complete with the exception of landscaping and punch list work.

Monday, November 22, 2010

Work is substantially complete with the exception of landscaping and punch list work.

Wednesday, November 10, 2010

The contractor is scheduled to complete the paving of the hot-mix asphalt surface course this week. Following the completing of the surface course, the contractor will work on driveway apron replacement, restoration, pavement markings and punch list work.

Friday, November 5, 2010

The contractor is scheduled to pave the hot-mix asphalt surface course early next week, starting Monday (weather permitting).

Monday, November 1, 2010

The contractor is scheduled to continue and finish grinding the existing asphalt pavement this week. Upon completion of the grinding, the contractor will work on manhole adjustments and prepare for paving the hot-mix asphalt surface course later this week or early next week (weather permitting).