Friday, October 22, 2010

The contractor is scheduled to continue work on utility structure adjustments and curb and gutter and sidewalk replacement late this week and possibly into next week. The contractor is scheduled to grind the existing asphalt pavement starting next week.

Friday, October 15, 2010

The contractor is scheduled to continue work on utility structure adjustments and curb and gutter and sidewalk replacement into next week. The contractor is scheduled to grind the existing asphalt pavement the end of this month/beginning of November.

Friday, October 8, 2010

The contractor is scheduled to continue work on utility structure adjustments and curb and gutter replacement into next week.

Friday, October 1, 2010

The contractor is scheduled to complete water services this week. The contractor is scheduled to continue work on utility structure adjustments and curb and gutter replacement into next week.