Monday, December 6, 2010

Work is substantially complete with the exception of punch list work.

Tuesday, November 30, 2010

Work is substantially complete with the exception of landscaping and punch list work.

Monday, November 22, 2010

Work is substantially complete with the exception of landscaping and punch list work.

Wednesday, November 10, 2010

The contractor is scheduled to complete the paving of the hot-mix asphalt surface course this week. Following the completing of the surface course, the contractor will work on driveway apron replacement, restoration, pavement markings and punch list work.

Friday, November 5, 2010

The contractor is scheduled to pave the hot-mix asphalt surface course early next week, starting Monday (weather permitting).

Monday, November 1, 2010

The contractor is scheduled to continue and finish grinding the existing asphalt pavement this week. Upon completion of the grinding, the contractor will work on manhole adjustments and prepare for paving the hot-mix asphalt surface course later this week or early next week (weather permitting).

Friday, October 22, 2010

The contractor is scheduled to continue work on utility structure adjustments and curb and gutter and sidewalk replacement late this week and possibly into next week. The contractor is scheduled to grind the existing asphalt pavement starting next week.

Friday, October 15, 2010

The contractor is scheduled to continue work on utility structure adjustments and curb and gutter and sidewalk replacement into next week. The contractor is scheduled to grind the existing asphalt pavement the end of this month/beginning of November.

Friday, October 8, 2010

The contractor is scheduled to continue work on utility structure adjustments and curb and gutter replacement into next week.

Friday, October 1, 2010

The contractor is scheduled to complete water services this week. The contractor is scheduled to continue work on utility structure adjustments and curb and gutter replacement into next week.

Friday, September 24, 2010

The contractor will continue completing water services and storm sewer work into next week. The contractor is scheduled to start utility structure adjustments and curb and gutter replacement in early October.

Friday, September 17, 2010

The sanitary sewer spot repairs have been completed this week. The contractor will continue completing water services into next week. The contractor is scheduled to start utility structure adjustments and curb and gutter replacement toward the end of this month.

Friday, September 10, 2010

The sanitary sewer spot repairs will continue through next week. Water main work will resume mid- to late next week.

Thursday, September 2, 2010

The sanitary structure repairs will probably take a few more weeks.

Friday, August 27, 2010

Storm sewer structures scheduled to be removed and replaced have all been completed. The contractor has moved on to removing and replacing sanitary sewer structures in Glenview Road. Flaggers are being used to direct traffic during this work and any delays should be minor.

Friday, August 20, 2010

All the water main crossings have been completed, meaning no more detour! However, the contractor may need to close down one lane of traffic at some point, but in that case flaggers will be used to help direct traffic.

Friday, August 13, 2010

Road Closure Next Week

The project includes water main repairs to the water mains that crosses Glenview Road. There is a new 10” water main that was recently installed (within the last several years) on the north side of Glenview Road. Since we are resurfacing the road, the water main crossings to the streets south of Glenview Road are being replaced and connected to this 10” main. There are five crossings to do. Glenview Road will be closed to all through traffic next week from Monday, August 16th, through Wednesday, August 18th, each day from 7 AM to 5 PM. Residents that have no other access than Glenview Road will of course be able to use the road. We just ask that extreme caution and patience be used around the construction!

Detour Via Central Road


View Larger Map

Project Description

This project includes the replacement of deteriorated manholes, water main repairs, some curb and gutter replacement, and the resurfacing of the road.